SCHEMES OF INPUT AND OPERATIONAL QUALITY CONTROL OF CONSTRUCTION AND INSTALLATION WORKS

Part IV, Issue 2

HEATING NETWORK

GEODETIC WORK

GEODETIC WORK WHEN LAYING PIPELINES

TECHNICAL REQUIREMENTS

SNiP 12-01-2004 Organization of construction.

SNiP 11-02-96. Engineering surveys for construction. Basic provisions.

SP 11-104-97 Engineering and geodetic surveys for construction.

GOST R 51872-2002 Executive geodetic documentation. Execution rules.

SNiP 3.01.03-84 Geodetic work in construction.

A manual for geodetic work in construction (to SNiP 3.01.03-84).

Geodetic work when laying pipelines is mandatory integral part technologies for the production of pipeline laying works (self-control, operational control and acceptance control).

Geodetic control means, along with mechanical ones, provide the ability to lay pipelines in the design position (self-control), provide the ability to monitor the compliance of the position of pipelines and its elements with design and regulatory requirements both during installation (operational control) and upon its completion (acceptance control by executive geodetic surveying the planned and altitude position of the laid pipeline).

Before starting work on laying the pipeline, it is necessary to check:


Availability of PPGR, technological map and SOKK or as part of the PPR technological documentation for carrying out geodetic work when laying pipelines, containing methods for performing detailed alignment work, a diagram of the location of signs, marks and landmarks, the order and volume of work performed;

Availability of a road layout certificate; the presence of an as-built drawing based on the results of staking out and fixing the places of connections and connections of communications, angles of rotation of the pipeline, wells, chambers, channels, tunnels, intersections of the pipeline with other networks;

Safety of signs of the external alignment network of the pipeline and axial signs, immutability of their position through repeated measurements of network elements; restoration of lost signs;

Availability of certificates of inspection of previously completed earthworks for the construction of trenches and pits, certificates of acceptance of trenches and pits;

Availability of an as-built drawing (scheme) based on the results of a geodetic check of the compliance of the planned and altitude positions of trenches and pits with the design ones; the presence in the drawing of confirmation by the customer of the correctness of the preparation and compliance of the as-built drawing with nature;

Conducting training for workers in labor organization and methods for aligning pipes and other pipeline elements horizontally and vertically.

Controlled Operations

Composition and controls

Documentation

Preparatory work

Check:

Availability of PPGR, technological map and SOKK, or as part of the PPR technological documentation for carrying out detailed alignment work when laying pipelines utility networks;

PPR, PPGR, technological map and SOKK

Availability of an as-built drawing based on the results of staking out the pipeline route;

As-built drawing

Preservation and invariability of the position of the pipeline network alignment signs, axial signs and signs that establish in nature the axis of the route, the beginning and end of the route, wells; restoration of lost signs;

General work log

Availability of inspection reports of previously completed earthworks and the act of acceptance of trenches and pits;

Certificates of inspection of hidden work

Availability of an as-built drawing based on the results of a geodetic as-built survey of completed trenches and pits with the customer’s permission to lay the pipeline.

As-built drawing

Geodetic work when laying pipelines

Control:

Compliance with the specified technology for geodetic work when laying pipelines;

Accuracy of marking work;

Geodetic control log

Laying pipes, wells, chambers, channels, tunnels in the design position (deviations in plan and height from the marks provided by the PPR using permanent and running sights, beacons, benchmarks, moorings, level, theodolite, laser devices).

Executive geodetic schemes

Check:

Compliance of the actual position of the pipeline and other structures with the requirements of the project and regulatory documents based on the results of instrumental geodetic survey;

As-built drawing

Proper execution of the as-built drawing based on the results of the as-built survey and receipt of confirmation by the customer of the correctness of the as-built drawing in situ.

INPUT AND OPERATIONAL CONTROL is carried out by:

foreman (foreman), surveyor - in the process of work

ACCEPTANCE CONTROL IS CARRIED OUT BY:

foreman (master), representatives of technical supervision of the customer and operating organizations

Instrumentation - level, theodolite, sights, wire, moorings, cast-offs, slats, measuring tape, laser devices and etc.

Geodetic work when laying pipelines is an integral part of the technological process of work. They must be carried out in accordance with the requirements of SNiP 3.01.03-84, PPR, PPGR, schemes operational control quality and other technological documentation of the quality management system operating in the enterprise.

Before starting work on laying pipelines, the position of the pipeline axis must be secured.

The axis of the route is projected into the trench with a theodolite or a plumb line from a tensioned wire between the pivot points of the axis or turning points.

Fixing the position of the axis of the route, especially wells, can be done using castings, arranged on straight sections of the route at a distance of 40-50 m from one another, as well as at turning points. For cast-offs ( edged boards, attached horizontally to the pillars above the trench, or inventory engineering cast-offs) take out and fix the axes between which the string is stretched. From the string, the axis is transferred by plumb lines to the bottom of the trench.

Laying out the design slope of the trench bottom after completing shortfalls and making up for overshoots and breaking out the bottom of pits for sealing pipeline joints can be done using permanent (fixed) and running sights, geometric leveling, optical levels and laser slope clamps. Marks of permanent (fixed) sights attached to inventory cast-offs, or nailed to a wooden cast-off, or installed on the edge of a trench, are made by a level taking into account the design slope of the trench..jpg" height="17"> - design slope of the trench, DIV_ADBLOCK866">


Laying out the height of the bottom of trenches, pits and pits and relocating the pipeline axis using fixed and moving sights

https://pandia.ru/text/80/203/images/image005_11.gif" width="418" height="198 src=">

1. Fixed cast-offs 2. Running sights 3. Fixed sights on the edge of the trench

When monitoring using the method of geometric leveling along the axis, every 15-20 m, stakes are driven in, placed at a convenient distance from the axis, they are leveled and on each mark the depth of the trench is written, calculated from the difference between the design mark and the mark of the peg. The depth of the trench is controlled by a rod with centimeter divisions, along which the clamp and slider are mixed. The clamp is fixed at a mark equal to the depth of the trench from the top cut of the peg.

Automatic regulation of the trench depth can be performed using various slope sensors installed on the earthmoving machine (pendulum, electronic level, gyroscope) or using slope sensors installed parallel to the axis of the route separately from the earthmoving machine (string, laser light beam).

Laying out a well pit includes securing the center of the well, installing a cast-off fixed at a distance of 0.6-0.7 m from the edge of the trench, and transferring marks and axes to the cast-off.

Laying pipes in height can be carried out:

When building on a prepared foundation (by beacons) according to the level;

Schemes of incoming and operational quality control of construction installation work. Part I, issue 2. Installation of prefabricated reinforced concrete structures residential buildings, installation of light enclosing structures. Trust "Orgtekhstroy-11" 2001
Schemes for incoming and operational quality control of construction and installation works are drawn up in accordance with the requirements of SNiP 3.01.01-85* “Organization of construction production”.
Schemes of incoming and operational control are intended for line engineering and technical workers, foremen and workers, employees of the quality control department of construction and installation work, workers of laboratory, geodetic and welding services who carry out self-control, incoming, operational and acceptance quality control of construction and installation work.
Schemes can be used:
- employees of services for the preparation of construction production as standard ones for their inclusion in projects for construction and installation works or the development on their basis of schemes that reflect the specifics of specific projects of buildings and structures;
- employees of personnel training services as teaching aid in training, retraining and advanced training of workers and engineers;
- teaching staff higher and secondary technical educational institutions in the training of engineering and technical workers in the construction industry;
- heads of departments, main functional departments and services, as well as management of construction organizations when testing knowledge of projects and regulatory requirements on the quality of construction and installation work performed by line personnel, as well as during inspection quality control of construction and installation work;
- employees of design supervision of design organizations;
- employees of the customer’s technical supervision who accept the work performed, employees of architectural and construction supervision services, federal and regional centers for licensing construction activities and other organizations supervising construction.


Schemes for incoming and operational quality control of construction and installation works are drawn up based on the requirements building codes and rules state standards, technical specifications, standard project documentation and contain:
- basic requirements for the quality of materials, structures and parts used;
- list technological operations subject to control during construction and installation work;
- a list of technical requirements that must be observed when performing construction and installation work;
- diagrams of the main assembly units;
- basic quality requirements for acceptance of completed stages and types of work.
Building construction, products, materials and engineering equipment arriving at the construction site must undergo entrance control. Work producers (craftsmen) are obliged to check, through external inspection and taking the necessary measurements, the conformity of the quality of incoming structures, products, materials and engineering equipment requirements of working drawings, state standards, technical specifications.
When performing incoming inspection at picking bases, the foreman (foreman) must be presented with documents (passports, certificates, acts, etc.) confirming the quality of the supplied materials and products. If there are any doubts about the quality of the supplied materials, the foreman (master) is obliged to demand control check received product materials.
Incoming control should prevent the launch into production of materials, structures and products that do not meet the requirements of design and regulatory technical documentation. On construction site Incoming inspection must be carried out by a foreman or foreman, with the involvement, if necessary, of laboratory and other services.
Operational control should be carried out during construction and installation work and ensure timely identification of defects and the causes of their occurrence, as well as timely adoption of measures to eliminate and prevent them.
When implementing operational control, the following must be checked:
- compliance with the work production technology specified in work projects and technological maps;
- compliance of the quality of work performed with the requirements of the project and regulatory and technical documentation.
Operational control must be carried out by the work foreman (foreman), engineer (laboratory assistant) of the construction laboratory, surveyor, welding service worker or welding laboratory worker. The participation of a particular service in the implementation of operational control should be regulated by a technological map for a specific technological process.
Acceptance inspection should be carried out upon completion of stages or individual species works, as well as critical structures. Acceptance is formalized by acts of inspection of hidden work, acts of acceptance of individual stages or types of work, as well as critical structures.
Acceptance must be carried out by a foreman, employees of the quality control department for construction and installation work, with the involvement, if necessary, of workers from laboratory, geodetic or welding services, and representatives of the customer’s technical supervision.
When carrying out production control, you must use measuring instruments and devices that have passed metrological verification in deadlines.
Links to normative literature are given as of December 25, 2000. Data on new normative documentation and changes to the current one are given in the information indexes of Gosstandart and Gosstroy of Russia.

Explanatory note.
Installation of reinforced concrete structures of residential buildings.
Off-site and on-site preparatory work.
Construction of a geodetic alignment basis for construction.
Construction of ground rail crane tracks.
- are common technical requirements.
- geodetic work during the construction of ground rail crane tracks.
- requirements for operation.
Incoming quality control of prefabricated concrete and reinforced concrete products and structures.
- GOST 13015.0-83* Prefabricated concrete and reinforced concrete structures and products. General technical requirements.
- GOST 13015.2-81* Prefabricated concrete and reinforced concrete structures and products. Marking.
- GOST 13015.3-81* Prefabricated concrete and reinforced concrete structures and products. Quality document.
- GOST 13015.4-84 Prefabricated concrete and reinforced concrete structures and products. Transportation and storage rules.
- GOST 11024-84* External concrete and reinforced concrete wall panels for residential and public buildings. Specifications.
- GOST 12504-80* Internal concrete and reinforced concrete wall panels for residential and public buildings. General technical conditions.
- GOST 26434-85** Reinforced concrete floor slabs for residential buildings. Types and basic parameters.
- GOST 9561-91 Reinforced concrete hollow-core floor slabs for buildings and structures. Technical conditions.
- GOST 12767-94 Solid reinforced concrete floor slabs for large-panel buildings. General technical conditions.
- GOST 9574-90 Gypsum concrete panels for partitions. Technical conditions.
- GOST 25098-87 Reinforced concrete partition panels for buildings of industrial and agricultural enterprises. Technical conditions.
- GOST 17079-88 Reinforced concrete ventilation blocks. Technical conditions.
- GOST 17538-82* Reinforced concrete structures and products for elevator shafts of residential buildings. Technical conditions.
- GOST 18048-80* Reinforced concrete sanitary cabins. Technical conditions.
- GOST 9818-85* Reinforced concrete flights and landings of stairs. Technical conditions.
Geodetic work on the original horizon.
Geodetic work on the installation horizon.
Installation of external wall panels.
Installation of internal wall panels.
Installation of floor slabs.
Assemblies of external walls made of single-layer lightweight concrete panels according to series 2.130-1 issue 26.
Installation of ventilation units.
Instructions for the installation of volumetric blocks of elevator shafts from the series 1.189.1-11 Reinforced concrete structures for passenger elevator shafts of residential buildings with a floor height of 3.0 m (issue 1 and 2)
Installation of volumetric blocks of elevator shafts.
Installation of sanitary cabins.
Installation of staircases and flights.
Installation of partition panels.
Mounting units for gypsum concrete partitions according to series 2.130-1 issue 27.
Mounting units reinforced concrete partitions according to series 2.130-1 issue 27.
Sealing of joints and seams.
Sealing of joints of large-panel residential buildings.
Insulation of joints between window blocks and walls according to series 1.132.1-17.
Anti-corrosion protection of embedded and connecting products.
Installation of partitions from plasterboard sheets and panels.
Series 1.131.9-24 “Partitions made of plasterboard sheets for residential buildings”, issue 3 “Partitions element-by-element assembly on metal frame with sound insulation made of mineral wool slabs, mineral wool broaching mats with details for laying electrical communications.”
Nodes plasterboard partitions according to series 1.131.9-24 issue. 3

In PDF and HTML formats. 5.8 MB.


SCHEMES OF INPUT AND OPERATIONAL QUALITY CONTROL OF CONSTRUCTION AND INSTALLATION WORKS

Part IV, Issue 2

HEATING NETWORK

TESTING AND WASHING OF HEATING NETWORKS PIPELINES


Technical requirements

SNiP 12-01-2004 Organization of construction.

SNiP 3.05.03-85 Heating network.

SNiP 12-04-2002 Labor safety in construction. Part 2. Construction production.

PB 10-573-03 Rules for the design and safe operation of steam and hot water.

SP 41-105-2002 Design and construction of ductless heating networks from steel pipes with industrial thermal insulation made of polyurethane foam in a polyethylene shell.

SP 41-106-2004 Design and installation of underground heating and hot water supply pipelines from asbestos-cement pipes.

SP 41-107-2004 Design and installation of underground hot water supply pipelines from PE-S pipes with thermal insulation from polyurethane foam in a polyethylene shell.

General provisions

Testing and flushing (purging) of heating network pipelines must be carried out in accordance with the requirements of the project, SNiP 3.05.03-85, SNiP 12-04-2002, PB 10-573-03, SP 41-105-2002, SP 41-106- 2004, SP 41-107-2004, PPR, technological maps, operational quality control schemes and other technological documentation approved in the prescribed manner and operating in the quality management system.

The safety of pipeline testing must be ensured based on the implementation of the following labor protection decisions contained in the organizational and technological documentation (POS, PPR, etc.):

Determination of the test program;

Safety measures when performing work in trenches, wells and at heights;

Special measures safety during pneumatic testing of pipelines.

Pipeline testing must be carried out under the direct supervision of a specially designated person from among specialists installation organization.

Before testing you must:

The work manager should familiarize the personnel participating in the tests with the procedure for carrying out the work and measures for their safe implementation;

Warn workers in adjacent areas about the time of testing;

Check instrumentation and plugs;

Fence the testing area and mark it with appropriate signs;

Check that there are no foreign objects inside the pipelines;

Mark temporary plugs, hatches and flange connections with warning signs;

Install posts at the rate of one post within sight of another, but at least every 200 m from each other, to warn about danger zone;

Determine the places and conditions for the safe stay of persons involved in testing;

Provide workplace illumination of at least 50 lux;

Determine the persons responsible for implementing the safety measures provided for in the test program.


Controlled Operations

Composition and controls

Documentation

Preparatory work

Check:

Availability of PPR, technological maps, operational quality control schemes (OQC), testing programs, implementation of occupational safety measures;


PPR, technological maps, SOKK, test program

- completion and proper registration of previous work on laying pipelines and welding butt joints and correction of detected defects, testing of welded joints, waterproofing of pipelines;

Certificates of inspection of hidden work with executive documentation; Test report

- completion of installation of equipment and instrumentation;

- installation of plugs at the ends of the tested pipelines and instead of compensators and sectional valves;

- readiness of means for filling, crimping and emptying the pipeline, completion of installation of temporary communications, installation of instruments and taps necessary for testing;

- availability of access to welded joints for their external inspection during testing;

Organization of duty at the border of the danger zone.


Testing and (purging) of heating network pipelines

Control:

Compliance with the specified production technology for testing pipelines for strength and tightness;


General and special work logs

- pressure drop during testing;

- the presence or absence of signs of rupture, leakage or fogging in welds, leaks in the base metal, flange connections, fittings, compensators and other elements of pipelines, signs of shift or deformation of pipelines and fixed supports;

- elimination of pipeline defects identified during testing and compliance with the technology for repeated testing of pipelines.

Acceptance

Check:

Compliance of test parameters and its results with the requirements of the project and regulatory documents;


Report on preliminary testing of the pipeline

- absence of defects in welds and connections;

- no signs of shift or deformation of pipelines and fixed supports;

- proper execution of the preliminary testing report.

INPUT AND OPERATIONAL CONTROL is carried out by:

foreman (master) - in the process of work

ACCEPTANCE CONTROL IS CARRIED OUT BY:

foreman (master), representatives of technical supervision of the customer and operating organization

Instrumentation - spring pressure gauges of class not lower than 1.5 and other equipment.


Simultaneous hydraulic test several pipelines mounted on the same supporting structures or overpass is allowed if support structures or overpasses are designed for appropriate loads (according to the PPR).

During pneumatic tests of pipelines located in trenches, a danger zone must be established, the value of which is indicated in the table below.


Pipe material

Test pressure, MPa

Pipeline diameter, mm

Distance from the edge of the trench and the ends of the pipelines to the boundary of the danger zone, m

Steel

0,6-1,6

up to 300

7,0

300-1000

10,0

St. 1000

20,0

Cast iron

0,15

up to 500

10,0

0,6

up to 500

15,0

0,15

St. 500

20,0

0,6

St. 500

25,0

Asbestos cement

0,15

up to 500

15,0

0,6

up to 500

20,0

0,15

St. 500

20,0

0,6

St. 500

25,0

When pipelines are located near residential or operated public or industrial buildings their pneumatic tests can be carried out under the condition that the window and door openings of these buildings, located within the danger zone, must be closed with protective barriers (shields, grilles).

The boundaries of the danger zone must be marked with signal barriers or safety signs.

The presence of persons in the danger zone during the period of air injection into the pipeline and when the pipeline is kept under pressure during strength testing is not allowed.

It is not allowed to carry out pneumatic tests of pipelines on racks, in channels and trays where existing pipelines are laid.

Work procedure

The test is allowed to begin only after timely warning of surrounding persons and obtaining permission from the test director.

During pneumatic testing of pipelines safety valves must be adjusted to the appropriate pressure.

Connection and disconnection of lines supplying air from the compressor to the pipeline under test is permitted only after the air supply has been stopped and the pressure has been reduced to atmospheric pressure.

Tapping welds directly during testing of pipelines is not allowed.

Inspection of pipelines is permitted only after pressure reduction, MPa:

up to 0.3 - in steel and plastic pipelines;

up to 0.1 - in cast iron and asbestos-cement pipelines.

Pipeline defects should be eliminated after the pressure has been reduced to atmospheric pressure.

When purging pipelines after testing, protective barriers (screens) must be installed in front of open hatches and fittings.

Requirements SNiP 3.05.03-85

After completion of construction and installation work, heating network pipelines must be subjected to final (acceptance) tests for strength and tightness. In addition, condensate pipelines and pipelines of water heating networks must be flushed, steam pipelines must be purged with steam, and pipelines of water heating networks must be open system heating and hot water supply networks - washed and disinfected.

Pipelines of heating networks laid without ducts and in non-passable channels are also subject to preliminary tests for strength and tightness during construction and installation work.

Preliminary tests of pipelines should be carried out before installing gland (bellows) compensators, sectional valves, closing channels and backfill channelless pipelines and channels.

Preliminary tests of pipelines for strength and tightness should be performed, as a rule, hydraulically.

At negative temperatures outside air and the impossibility of heating water, as well as in the absence of water, it is allowed, in accordance with the PPR, to perform preliminary tests using a pneumatic method.

It is not allowed to carry out pneumatic tests of pipelines laid in the same channel (section) or in the same trench with existing engineering communications.

Pipelines of water heating networks should be tested at a pressure equal to 1.25 working, but not less than 1.6 MPa (16 kgf/cm), steam pipelines, condensate pipelines and hot water supply networks - at a pressure equal to 1.25 working, unless other requirements are justified by the design (working project).

Before performing strength and tightness tests, you must:

Carry out quality control of welded joints of pipelines and correction of detected defects;

Disconnect the tested pipelines from the existing ones and from the first one using plugs. shut-off valves installed in a building (structure);

Install plugs at the ends of the tested pipelines and instead of stuffing box (bellows) compensators, sectional valves - during preliminary tests;

Provide access throughout the entire length of the pipelines being tested for their external inspection and inspection of welds during the tests;

Open the valves and bypass lines completely.

The use of shut-off valves to disconnect the pipelines under test is not permitted.

Simultaneous preliminary tests of several pipelines for strength and tightness are allowed to be carried out in cases justified by the PPR.

Pressure measurements when testing pipelines for strength and tightness should be made using two duly certified (one control) spring pressure gauges of class not lower than 1.5 with a body diameter of at least 160 mm and a scale with a nominal pressure of 4/3 of the measured pressure.

Testing of pipelines for strength and tightness (density), their purging, washing, disinfection must be carried out according to technological schemes(agreed with operating organizations) regulating the technology and safety precautions for carrying out work (including the boundaries security zones).

Reports of the established form should be drawn up on the results of tests of pipelines for strength and tightness, as well as on their flushing (purging).

11.9.1 During production processes and operations, operational controls are carried out in order to identify defects that may be hidden if the process or operation continues, and to take measures to prevent and eliminate these defects.

11.9.2 With operational control, the person carrying out construction checks:

Compliance of the sequence and composition of the technological operations performed with the technological and regulatory documentation applicable to these technological operations;

Compliance with technological regimes established by technological maps and regulations;

Compliance of quality indicators of operations and their results with the requirements of design and technological documentation, as well as regulatory documentation applicable to these technological operations.

11.9.2 During the construction process, an assessment of the work performed, the results of which affect safety, must be carried out object, but in accordance with the adopted technology become unavailable for control after the start of subsequent work, as well as completed building structures and sections of utility networks, the elimination of defects identified by inspection is impossible without dismantling or damaging subsequent structures and sections of utility networks. Representatives of the relevant state supervision bodies, designer’s supervision, as well as, if necessary, independent experts may participate in these control procedures. The contractor notifies the other participants of the timing of these procedures no later than three working days in advance.

11.9.3 The results of acceptance of work hidden by subsequent work, in accordance with the requirements of design and regulatory documentation, are documented in certificates of inspection of hidden work ( Appendix M ). The developer (customer) may require a re-inspection after eliminating the identified defects.

11.9.4 To the conformity assessment procedure individual designs, tiers of structures (floors), the contractor must submit inspection reports of all hidden work included in these structures, geodetic as-built diagrams, as well as test reports for structures in cases provided for in the design documentation and (or) the construction contract. The developer (customer) can check the accuracy of the as-built geodetic schemes presented by the contractor. For this purpose, the performer of the work must preserve the alignment axes and installation guidelines fixed in kind until the completion of acceptance.

The results of acceptance of individual structures must be documented in acceptance certificates for critical structures ( Appendix N ).

11.9.5 Tests of sections of utility networks and installed utility equipment are carried out in accordance with the requirements of the relevant regulatory documents and are documented in acceptance certificates for critical structures (Appendix H).

11.9.6 If defects in work, structures, or sections of utility networks are discovered as a result of stage-by-stage acceptance, the corresponding acts must be drawn up only after the identified defects have been eliminated.

In cases where subsequent work must begin after a break of more than 6 months from the completion of phased acceptance, before resuming work, these procedures should be repeated with the execution of the relevant acts.

11.9.7 Places for performing control operations, their frequency, performers, methods and measuring instruments, forms for recording results, the procedure for making decisions when identifying non-compliance with established requirements must comply with the requirements of design, technological and regulatory documentation.

11.9.8 The person carrying out the construction appoints with his administrative documents the responsible executors for performing operational control, documenting its results and eliminating defects identified by the control.

The results of operational control must be documented in special work logs.

The price for this document is not yet known. Click the "Buy" button and place your order and we will send you the price.

Distributing regulatory documentation since 1999. We punch checks, pay taxes, accept all legal forms of payment without additional interest. Our clients are protected by law. LLC "CNTI Normocontrol"

Our prices are lower than other places because we work directly with document providers.

Delivery methods

  • Urgent Express delivery(1-3 days)
  • Courier delivery (7 days)
  • Pickup from the Moscow office
  • Russian Post

The manual is intended for customers (developers), construction and installation organizations, specialists of state construction supervision, as well as engineering and technical workers directly involved in the construction of buildings and structures

  • Replaces Schemes for operational quality control of construction, repair, construction and installation works

Introduction

Regulatory documents regulating the quality of construction and installation works, building materials, products and structures

Methods of testing and quality control of building materials, products and structures during construction and installation work

Part 1. Construction work

A. Earthworks

1. Development of excavations (trenches) for structures

2. Development of pits using excavators

3. Development of trenches for pipelines in non-rocky soils

4. Postback

5. Vertical layout

6. Construction of embankments

B. Construction of foundations

7. Installation of strip foundation blocks

8. Installation of wall blocks in the underground part of buildings

9. Installation of glass-type foundation blocks

10. Construction of pile foundations

11. Arrangement of prefabricated grillages

12. Installation of monolithic grillages

13. Installation of horizontal waterproofing of foundations made of cement mortars

B. Concrete work

14. Installation of inventory formwork

15. Reinforcement work

16. Laying concrete mixtures

17. Construction of monolithic concrete and reinforced concrete walls

18. Construction of monolithic concrete and reinforced concrete columns

19. Construction of monolithic concrete and reinforced concrete foundations

G. Stone work

20. Wall masonry

21. Laying partitions

22. Laying pillars

D. Installation work

23. Installation of reinforced concrete columns of one-story buildings

24. Installation of prefabricated reinforced concrete columns of multi-storey buildings

25. Installation of reinforced concrete crossbars, beams, trusses

26. Installation of floor slabs and coverings

27. Installation flights of stairs and sites

28. Installation balcony slabs and jumpers

29. Installation of external wall panels of frame buildings

30. Installation of panels, blocks load-bearing walls buildings

31. Installation of volumetric blocks of elevator shafts

32. Installation of prefabricated reinforced concrete ventilation blocks

33. Installation of volumetric blocks

34. Installation of sanitary cabins

35. Installation of gypsum concrete partitions

36. Installation of asbestos-cement extrusion panels and slabs

37. Installation of frame-sheathing partitions

38. Installation of walls from sandwich panels and sheet assembly

39. Welding of installation connections of reinforced concrete structures

40. Anti-corrosion protection of steel embedded products

41. Sealing joints

42. Caulking joints and seams

43. Construction of a garbage chute

E. Roofing and insulation work

44. Preparation of foundations and underlying insulation and roofing elements

45. Thermal insulation device from bulk materials

46. ​​Installation of thermal insulation from slabs

47. Insulation device made from rolled materials

48. Insulation device made of polymer and emulsion-bitumen compositions

49. Roofing from rolled materials

50. Roofing from piece materials

51. Construction of a roof made of polymer and emulsion-bitumen compositions

52. Installation of a metal roof

G. Carpentry work

53. Installation of window blocks

54. Installation of door blocks

55. Construction of mezzanines, cabinets

H. Floor installation

56. Preparation of soil foundations for floors

57. Construction of a concrete underlying layer, screeds

58. Floor soundproofing device

59. Installation of glued floor waterproofing

60. Device bitumen waterproofing gender

61. Installation of monolithic coatings

62. Installation of ceramic tile floors

63. Installation of mosaic floors

64. Installation of floors made of polymer materials

65. Laying joists in floors on floor slabs

66. Laying logs on posts on the ground base

67. Installation of plank floors

68. Installation of block parquet floors

69. Installation of floors from panel parquet

I. Finishing work

70. Plastering works(simple plaster)

71. Plastering works (improved plaster)

72. Plastering works (high-quality plaster)

73. Plastering works (coatings made of sheets of dry gypsum plaster)

74. Painting work (painting with water-based compositions)

75. Painting work (painting with waterless compounds)

76. Cladding work

77. Wallpaper work

78. Glass work (glazing of bindings)

79. Glass work (installation of glass blocks and glass panels)

80. Installation of fiberglass fencing

81. Finishing (cladding) walls with panels, sheets with factory finishing

82. Montage suspended ceilings in building interiors

K. Improvement

83. Drainage device

84. Construction of a blind area made of concrete and asphalt concrete

85. Construction of sidewalks and paths from slabs

86. Construction of crushed stone base and asphalt concrete pavement

Part 2. Repair and construction work

1. Repair and strengthening of old foundations

2. Laying prefabricated reinforced concrete slabs floors during reconstruction of brick buildings

3. Construction of monolithic sections in floors

4. Installation of floor slabs on metal beams

5. Strengthening brick pillars and piers

6. Installation of metal jumpers

7. Installation of stairs on metal stringers

8. Device rafter system made of wooden elements

9. Plaster repair

10. Repair of plastering of building facades

11. Painting facades

12. Installation of molded parts of facades

13. Installation of drainpipes

Part 3. Installation work

1. Making holes and grooves for laying pipelines

2. Installation of cast iron pressure pipelines

3. Installation of pressure pipelines from asbestos-cement pipes

4. Installation of internal cold and hot water supply pipelines

5. Installation of reinforced concrete and concrete non-pressure pipelines

6. Installation of sewer pipelines from ceramic pipes

7. System installation internal sewerage and drainage

8. Installation of water fittings

9. Installation of bathtub and washbasin

10. Installation of sanitary fixtures

11. Installation of an internal heating system

12. Installation of metal air ducts

13. Electric lighting device

14. Construction of round reinforced concrete wells

15. Installation of heating main cameras

16. Installation of non-passable channels

17. Insulation of heating pipelines