Installation of heating networks. Calculation of thermal expansion of pipelines Calculation of expansion of expansion joints of heating networks

4.1. Installation of pipelines must be carried out by specialized installation organizations, while the installation technology must ensure high operational reliability of pipelines.

4.2. Parts and elements of pipelines (compensators, mud traps, insulated pipes, as well as pipeline units and other products) must be manufactured centrally (in factories, workshops, workshops) in accordance with standards, technical specifications and design documentation.

4.3. The laying of pipelines in a trench, channel or on above-ground structures should be carried out using the technology provided for by the work project and excluding the occurrence of residual deformations in the pipelines, violation of the integrity of the anti-corrosion coating and thermal insulation by using appropriate installation devices, correct placement of simultaneously operating lifting machines and mechanisms.

The design of fastening mounting devices to pipes must ensure the safety of the coating and insulation of pipelines.

4.4. The laying of pipelines within the panel support must be carried out using pipes of the maximum delivery length. In this case, the transverse welds of the pipelines should, as a rule, be located symmetrically relative to the panel support.

4.5. Laying of pipes with a diameter of over 100 mm with a longitudinal or spiral seam should be carried out with an offset of these seams by at least 100 mm. When laying pipes with a diameter of less than 100 mm, the displacement of the seams must be at least three times the thickness of the pipe wall.

Longitudinal seams must be within the upper half of the circumference of the pipes being laid.

Steeply curved and stamped pipeline bends are allowed to be welded together without a straight section.

Welding of pipes and bends into welded joints and bent elements is not allowed.

4.6. When installing pipelines, the movable supports and hangers must be shifted relative to the design position by the distance specified in the working drawings, in the direction opposite to the movement of the pipeline in working condition.

In the absence of data in the working drawings, the movable supports and hangers of horizontal pipelines must be shifted taking into account the correction for the outside air temperature during installation by the following values:

sliding supports and elements for fastening hangers to the pipe - by half the thermal elongation of the pipeline at the attachment point;

roller bearing rollers - by a quarter of thermal elongation.

4.7. When installing pipelines, spring hangers must be tightened in accordance with the working drawings.

When performing hydraulic tests of steam pipelines with a diameter of 400 mm or more, an unloading device should be installed in spring suspensions.

4.8. Pipe fittings must be installed in a closed state. Flange and welded connections of fittings must be made without tension in the pipelines.

The deviation from the perpendicularity of the plane of the flange welded to the pipe relative to the pipe axis should not exceed 1% of the outer diameter of the flange, but be no more than 2 mm at the top of the flange.

4.9. Bellows (wavy) and stuffing box expansion joints should be installed assembled.

At underground installation heating networks, installation of compensators in the design position is allowed only after preliminary tests of pipelines for strength and tightness, backfilling of channelless pipelines, channels, chambers and panel supports.

4.10. Axial bellows and stuffing box expansion joints should be installed on pipelines without breaking the axes of the expansion joints and the axes of the pipelines.

Permissible deviations from the design position of the connecting pipes of compensators during their installation and welding should be no more than those specified in the technical specifications for the manufacture and supply of compensators.

4.11. When installing bellows expansion joints, they are not allowed to twist relative to the longitudinal axis and sag under the influence of their own weight and the weight of adjacent pipelines. Slinging of expansion joints should be done only by the pipes.

4.12. The installation length of bellows and stuffing box expansion joints must be taken according to the working drawings, taking into account corrections for the outside air temperature during installation.

Stretching of expansion joints to the installation length should be done using devices provided for in the design of expansion joints, or tensioning mounting devices.

4.13. Stretching of the U-shaped compensator should be performed after completion of pipeline installation, quality control of welded joints (except for closing joints used for tension) and fastening of fixed support structures.

The compensator should be stretched by the amount indicated in the working drawings, taking into account the correction for the outside air temperature when welding the closing joints.

Stretching of the compensator must be carried out simultaneously on both sides at joints located at a distance of no less than 20 and no more than 40 pipeline diameters from the axis of symmetry of the compensator, using tension devices, unless other requirements are justified by the design.

On the section of the pipeline between the joints used for stretching the compensator, there should be no preliminary displacement of supports and hangers in comparison with the design (detailed design).

4.14. Immediately before assembling and welding pipes, it is necessary to visually inspect each section to ensure that there are no foreign objects or debris in the pipeline.

4.15. The deviation of the pipeline slope from the design one is allowed by ± 0.0005. In this case, the actual slope must be no less than the minimum allowable according to SNiP II-G.10-73* (II-36-73*).

The movable supports of pipelines must be adjacent to the supporting surfaces of the structures without gaps or distortion.

4.16. When performing installation work, the following types of hidden work are subject to acceptance with drawing up inspection reports in the form given in SNiP 3.01.01-85: preparation of the surface of pipes and welded joints for anti-corrosion coating; performing anti-corrosion coating of pipes and welded joints.

A report on the stretching of compensators should be drawn up in the form given in the mandatory Appendix 1.

4.17. Protection of heating networks from electrochemical corrosion must be carried out in accordance with the Instructions for the protection of heating networks from electrochemical corrosion, approved by the USSR Ministry of Energy and the Ministry of Housing and Utilities of the RSFSR and agreed with the USSR State Construction Committee.

The amount of displacement (compensating capacity) of compensators is usually expressed as a combination of positive and negative numerical values ​​(±). A negative (-) value indicates the permissible compression of the compensator, a positive (+) value indicates its permissible stretch. Sum absolute values of such values ​​represents the total displacement of the compensator. In most cases, compensators work in compression, compensating for the thermal expansion of pipelines, less often (refrigerated media and cryogenic products) - in tension.

Preliminary stretching during installation is necessary for the rational use of the full displacement of the compensator, depending on the nature of the pipeline, installation conditions and the prevention of stress conditions.

The peak expansion values ​​of the pipeline depend on the minimum and maximum temperatures of its operation. For example, the minimum operating temperature of the pipeline is Tmin = 0°C and the maximum Tmax = 100°C. Those. temperature difference At = 100°C. With a pipeline length L equal to 90 m, the maximum value of its extension to the pipeline AL will be 100 mm. Let’s imagine that for installation on such a pipeline, compensators with an offset of ±50 mm are used, i.e. with a total offset of 100 mm. Also, imagine that the temperature environment at the stage of their installation, T y is equal to 20°C. The nature of the compensator's operation under such conditions will be as follows:

  • at 0°C - the compensator will be stretched by 50 mm
  • at 100°C - the compensator will be compressed by 50 mm
  • at 50°C - the compensator will be in a free state
  • at 20°C - the compensator will be stretched by 30 mm

Consequently, preliminary stretching of 30 mm during installation (T y = 20°C) will ensure its effective operation. When the temperature rises from 20°C to 50°C during commissioning of the pipeline, the compensator will return to the free (unstressed) state. When the pipeline temperature increases from 50°C to 100°C, the displacement of the compensator from the relatively free state towards compression will be an estimated 50 mm.

Definitionvaluespreliminarysprains

Let's assume the pipeline length is 33 meters, the maximum/minimum operating temperature is +150°C /-20°C, respectively. With such a temperature difference, the coefficient of linear expansion a will be 0.012 mm/m*°C.

The maximum extension of the pipeline can be calculated as follows:

ΔL = αxLxΔ t = 0.012 x 33 x 170 = 67 mm

The pre-stretch value PS is determined by the formula:

PS = (ΔL/2) - ΔL (Ty-Tmin): (Tmax-Tmin)

Thus, during the installation of the compensator, it must be installed with a pre-stretch PS equal to 18 mm.

In Fig. Figure 1 shows the distance required for installing the compensator in the pipeline line, defined as the sum of the values ​​of the compensator length lq in the free state and pre-stretch PS.

In Fig. 2 shows that during installation, on one side the compensator is fixed with a flange or welded.

Compensation devices in heating networks they serve to eliminate (or significantly reduce) the forces that arise during thermal elongation of pipes. As a result, stresses in the pipe walls and forces acting on equipment and supporting structures are reduced.

The elongation of pipes as a result of thermal expansion of the metal is determined by the formula

Where A- coefficient of linear expansion, 1/°С; l- pipe length, m; t - working temperature walls, 0 C; t m - installation temperature, 0 C.

To compensate for the elongation of pipes, special devices are used - compensators, and they also use the flexibility of pipes at turns in the route of heating networks (natural compensation).

According to the principle of operation, compensators are divided into axial and radial. Axial compensators are installed on straight sections of the heat pipeline, since they are designed to compensate for forces arising only as a result of axial elongations. Radial compensators are installed on heating networks of any configuration, as they compensate for both axial and radial forces. Natural compensation does not require the installation of special devices, so it must be used first.

They are used in heating networks axial expansion joints two types: omental and lens. In stuffing box compensators (Fig. 29.3), thermal deformations of the pipes lead to the movement of the glass 1 inside the housing 5, between which the stuffing box packing 3 is placed for sealing. The packing is clamped between the thrust ring 4 and the ground bushing 2 using bolts 6.

Figure 19.3 Stuffing box expansion joints

a - one-sided; b - double-sided: 1 - glass, 2 - ground box, 3 - stuffing box,

4 - thrust ring, 5 - body, 6 - tightening bolts

An asbestos printed cord or heat-resistant rubber is used as an omental packing. During operation, the packing wears out and loses its elasticity, so periodic tightening (clamping) and replacement are required. To make it possible to carry out these repairs, stuffing box compensators are placed in chambers.

The connection of expansion joints to pipelines is carried out by welding. During installation, it is necessary to leave a gap between the collar of the cup and the thrust ring of the body, eliminating the possibility of tensile forces in the pipelines if the temperature drops below the installation temperature, and also carefully align the center line to avoid distortions and jamming of the cup in the body.

Stuffing box expansion joints are made one-sided and two-sided (see Fig. 19.3, a and b). Double-sided ones are usually used to reduce the number of chambers, since a fixed support is installed in the middle of them, separating sections of pipes, the extensions of which are compensated by each side of the compensator.

The main advantages of stuffing box expansion joints are their small dimensions (compactness) and low hydraulic resistance, as a result of which they are widely used in heating networks, especially for underground installation. In this case, they are installed at d y =100 mm or more, for overhead installation - at d y =300 mm or more.

In lens compensators (Fig. 19.4), with thermal elongation of pipes, special elastic lenses (waves) are compressed. This ensures complete tightness in the system and does not require maintenance of expansion joints.

Lenses are made from sheet steel or stamped half-lenses with a wall thickness of 2.5 to 4 mm by gas welding. To reduce hydraulic resistance, a smooth pipe (jacket) is inserted inside the compensator along the waves.

Lens compensators have a relatively small compensating capacity and a large axial reaction. In this regard, to compensate for temperature deformations of heating network pipelines, a large number of waves are installed or they are pre-stretched. They are usually used up to pressures of approximately 0.5 MPa, since at high pressures swelling of waves is possible, and increasing the rigidity of waves by increasing the thickness of the walls leads to a decrease in their compensating ability and an increase in the axial reaction.

Cassock. 19.4. Lens three-wave compensator

Natural compensation temperature deformations occur as a result of bending of pipelines. Bent sections (turns) increase the flexibility of the pipeline and increase its compensating ability.

With natural compensation at turns in the route, temperature deformations of pipelines lead to lateral displacements of sections (Fig. 19.5). The amount of displacement depends on the location of the fixed supports: than longer length section, the greater its elongation. This requires an increase in the width of the channels and complicates the operation of the movable supports, and also does not make it possible to use modern channelless laying at the turns of the route. The maximum bending stresses occur at the fixed support of a short section, since it is displaced by a large amount.

Rice. 19.5 Scheme of operation of the L-shaped section of the heat pipeline

A– with equal shoulder lengths; b– at different shoulder lengths

TO radial expansion joints, used in heating networks, include flexible And wavy hinged type. In flexible expansion joints, thermal deformations of pipelines are eliminated by bending and torsion of specially bent or welded sections of pipes various configurations: U- and S-shaped, lyre-shaped, omega-shaped, etc. U-shaped compensators are most widespread in practice due to ease of manufacture (Fig. 19.6a). Their compensating ability is determined by the sum of deformations along the axis of each pipeline section ∆ l= ∆l/2+∆l/2. In this case, the maximum bending stresses occur in the section furthest from the pipeline axis - the back of the compensator. The latter, bending, shifts by an amount y, by which it is necessary to increase the dimensions of the compensatory niche.

Rice. 19.6 Scheme of operation of the U-shaped compensator

A– without preliminary stretching; b– with pre-stretching

To increase the compensating capacity of the compensator or reduce the amount of displacement, it is installed with preliminary (assembly) stretching (Fig. 19.6, b). In this case, the back of the compensator when not in use is bent inward and experiences bending stresses. When the pipes are lengthened, the compensator first comes to a stress-free state, and then the back bends outward and bending stresses of the opposite sign arise in it. If in extreme positions, i.e. during pre-stretching and in working condition, the maximum permissible stresses, then the compensating capacity of the compensator doubles compared to a compensator without pre-stretching. In the case of compensation for the same temperature deformations in the compensator with pre-stretching, the backrest will not shift outward and, consequently, the dimensions of the compensatory niche will decrease. The operation of flexible compensators of other configurations occurs in approximately the same way.

Pendants

Pipeline hangers (Fig. 19.7) are carried out using rods 3, connected directly to pipes 4 (Fig. 19.7, A) or with a traverse 7 , to which on clamps 6 pipe is suspended (Fig. 19.7, b), as well as through spring blocks 8 (Fig. 19.7, V). Swivel joints 2 ensure the movement of pipelines. The guide cups 9 of the spring blocks, welded to the support plates 10, make it possible to eliminate the transverse deflection of the springs. The suspension tension is ensured using nuts.

Rice. 19.7 Pendants:

A– traction; b– clamp; V– spring; 1 – support beam; 2, 5 – hinges; 3 – traction;

4 - pipe; 6 – clamp; 7 – traverse; 8 – spring suspension; 9 – glasses; 10 – plates

3.4 Methods for insulating heating networks.

Mastic insulation

Mastic insulation is used only when repairing heating networks laid either indoors or in passage channels.

Mastic insulation is applied in layers of 10-15 mm to the hot pipeline as the previous layers dry. Mastic insulation cannot be performed using industrial methods. Therefore, the specified insulating structure is not applicable for new pipelines.

Sovelite, asbestos and vulcanite are used for mastic insulation. The thickness of the thermal insulation layer is determined on the basis of technical and economic calculations or according to current standards.

The temperature on the surface of the insulating structure of pipelines in passage channels and chambers should not exceed 60° C.

The durability of the thermal insulation structure depends on the operating mode of the heat pipes.

Block insulation

Prefabricated block insulation from pre-formed products (bricks, blocks, peat slabs, etc.) is installed on hot and cold surfaces. Products with bandaged seams in rows are laid on a mastic base made of asbozurite, the thermal conductivity coefficient of which is close to the coefficient of the insulation itself; The underlay has minimal shrinkage and good mechanical strength. Peat products (peat slabs) and corks are laid on bitumen or iditol glue.

Thermal insulation products are secured to flat and curved surfaces with steel studs, pre-welded in a checkerboard pattern at intervals of 250 mm. If installation of studs is not possible, the products are fixed as mastic insulation. On vertical surfaces with a height of more than 4 m, unloading support belts made of strip steel are installed.

During the installation process, the products are adjusted to each other, marked and holes for the studs are drilled. The mounted elements are secured with studs or wire twists.

With multi-layer insulation, each subsequent layer is laid after leveling and securing the previous one, overlapping the longitudinal and transverse seams. The last layer, secured with a frame or metal mesh, is leveled with mastic under the lath and then 10 mm thick plaster is applied. Pasting and painting are carried out after the plaster has completely dried.

The advantages of prefabricated block insulation are industrial, standard and prefabricated, high mechanical strength, the possibility of lining hot and cold surfaces. Disadvantages: multiple seams and complexity of installation.

Backfill insulation

On horizontal and vertical surfaces building structures Loose fill insulation is used.

When installing thermal insulation on horizontal surfaces (attic roofs, ceilings above the basement), the insulating material is predominantly expanded clay or perlite.

On vertical surfaces, fill-in insulation is made of glass or mineral wool, diatomaceous earth, perlite sand, etc. To do this, the parallel insulated surface is fenced with bricks, blocks or nets and insulating material is poured (or stuffed) into the resulting space. When using mesh fencing, the mesh is attached to studs pre-installed in a checkerboard pattern with a height corresponding to the specified insulation thickness (with an allowance of 30...35 mm). A metal woven mesh with a cell of 15x15 mm is stretched over them. Bulk material is poured into the resulting space layer by layer from bottom to top with light compaction.

After backfilling is completed, the entire surface of the mesh is covered with a protective layer of plaster.

Loose-fill insulation is quite effective and simple to install. However, it is not resistant to vibration and is characterized by low mechanical strength.

Cast insulation

As insulating material Foam concrete is mainly used, which is prepared by mixing cement mortar with foam mass in a special mixer. The thermal insulation layer is laid using two methods: conventional methods of concreting the space between the formwork and the insulated surface or shotcrete.

With the first method Formwork is placed parallel to the vertical insulated surface. The heat-insulating composition is placed in rows into the resulting space, leveling with a wooden trowel. The laid layer is moistened and covered with mats or matting to ensure normal conditions hardening of foam concrete.

Shotcrete method cast insulation is applied over mesh reinforcement made of 3-5 mm wire with cells of 100-100 mm. The applied shotcrete layer fits tightly to the insulated surface and has no cracks, cavities or other defects. Shotcrete is carried out at a temperature not lower than 10°C.

Cast thermal insulation is characterized by simplicity of design, solidity, and high mechanical strength. The disadvantages of cast thermal insulation are the long duration of the device and the impossibility of working at low temperatures.

SNiP 3.05.03-85
________________
Registered by Rosstandart as SP 74.13330.2011. -
Database manufacturer's note.

BUILDING REGULATIONS

HEATING NETWORK

Date of introduction 1986-07-01

DEVELOPED by the Orgenergostroy Institute of the USSR Ministry of Energy (L. Ya. Mukomel - topic leader; Candidate of Technical Sciences S. S. Yakobson).

INTRODUCED by the USSR Ministry of Energy.

PREPARED FOR APPROVAL BY Glavtekhnormirovanie Gosstroy USSR (N. A. Shishov).

APPROVED by Decree of the USSR State Committee for Construction Affairs dated October 31, 1985 N 178.

With the entry into force of SNiP 3.05.03-85 “Heating networks”, SNiP III-30-74 “Water supply, sewerage and heat supply. External networks and structures” loses its force.

AGREED with the State Mining and Technical Supervision Committee of the USSR on April 15, 1985.

These rules apply to the construction of new, expansion and reconstruction of existing heating networks,

transporting hot water at temperature t
and steam at temperature t

200 degrees C and pressure
440 degrees C and pressure

2.5 MPa (25 kgf/sq.cm)
6.4 MPa (64 kgf/sq.cm)

from the source of thermal energy to heat consumers (buildings, structures).

1. GENERAL PROVISIONS

1. GENERAL PROVISIONS

1.1. When constructing new, expanding and reconstructing existing heating networks, in addition to the requirements of working drawings, work plans (WPP) and these rules, the requirements of SNiP 3.01.01-85, SNiP 3.01.03-84, SNiP III-4-80 and standards must also be observed .

1.2. Work on the manufacture and installation of pipelines, which are subject to the requirements of the Rules for the Construction and Safe Operation of Steam and Hot Water Pipelines of the USSR Gosgortekhnadzor (hereinafter referred to as the Rules of the USSR Gosgortekhnadzor), must be carried out in accordance with the specified Rules and the requirements of these rules and regulations.

1.3. Completed construction heating network should be put into operation in accordance with the requirements of SNiP III-3-81.

2. EARTHWORK

2.1. Excavation and foundation work must be carried out in accordance with the requirements of SNiP III-8-76, SNiP 3.02.01-83, SN 536-81 and this section.

2.2. The smallest width of the trench bottom for channelless pipe laying should be equal to the distance between the outer side edges of the insulation of the outermost pipelines of heating networks (associated drainage) with an addition on each side for pipelines of a nominal diameter

The width of the pits in the trench for welding and insulation of pipe joints during channelless laying of pipelines should be taken equal to the distance between the outer side edges of the insulation of the outermost pipelines with the addition of 0.6 m on each side, the length of the pits - 1.0 m and the depth from the bottom edge of the pipeline insulation - 0.7 m, unless other requirements are justified by working drawings.

2.3. The smallest width of the trench bottom for channel laying of heating networks should be equal to the width of the channel taking into account the formwork (on monolithic areas), waterproofing, associated drainage and drainage devices, trench fastening structures with an addition of 0.2 m. In this case, the width of the trench must be at least 1.0 m.

If it is necessary for people to work between the outer edges of the canal structure and the walls or slopes of the trench, the width between the outer edges of the canal structure and the walls or slopes of the trench in the clear must be at least: 0.70 m - for trenches with vertical walls and 0.30 m - for trenches with slopes.

2.4. Backfilling of trenches during channelless and channel laying of pipelines should be carried out after preliminary tests of pipelines for strength and tightness, complete completion of insulation and construction and installation work.

Backfilling must be done in the specified technological sequence:

tamping of sinuses between pipelines of channelless laying and the base;

simultaneous uniform filling of the sinuses between the walls of the trench and pipelines during channelless installation, as well as between the walls of the trench and channel, chamber during channel installation to a height of at least 0.20 m above the pipelines, channels, chambers;

backfilling the trench to the design marks.

Backfilling of trenches (pits) to which additional external loads are not transferred (except for the own weight of the soil), as well as trenches (pits) at intersections with existing underground communications, streets, roads, driveways, squares and other structures of settlements and industrial sites should be carried out in accordance with the requirements of SNiP III-8-76.

2.5. After turning off temporary water reduction devices, channels and chambers must be visually inspected for the absence of groundwater.

3. CONSTRUCTIONS AND INSTALLATION OF BUILDING STRUCTURES

3.1. Work on the construction and installation of building structures should be carried out in accordance with the requirements of this section and the requirements of:

SNiP III-15-76 - for the construction of monolithic concrete and reinforced concrete structures foundations, supports for pipelines, chambers and other structures, as well as when grouting joints;

SNiP III-16-80 - for installation of prefabricated concrete and reinforced concrete structures;

SNiP III-18-75 - during installation metal structures supports, spans for pipelines and other structures;

SNiP III-20-74 - for waterproofing channels (chambers) and other building structures (structures);

SNiP III-23-76 - for the protection of building structures from corrosion.

3.2. The outer surfaces of channel and chamber elements supplied to the route must be covered with a coating or adhesive waterproofing in accordance with working drawings.

The installation of channel elements (chambers) in the design position should be carried out in a technological sequence linked to the project for the installation and preliminary testing of pipelines for strength and tightness.

Support pads for sliding supports of pipelines must be installed at the distances specified in SNiP II-G. 10-73* (II-36-73*).

3.3. Monolithic fixed panel supports must be made after installation of pipelines in the panel support area.

3.4. In places where channelless pipelines are inserted into channels, chambers and buildings (structures), the cases of bushings must be put on the pipes during their installation.

At the entrances of underground pipelines into buildings, devices must be installed (in accordance with the working drawings) to prevent gas from penetrating into the buildings.

3.5. Before installing the upper trays (plates), the channels must be cleared of soil, debris and snow.

3.6. Deviation of the slopes of the bottom of the heating network channel and drainage pipelines from the design is allowed by +/- 0.0005, while the actual slope must be no less than the minimum allowable according to SNiP II-G.10-73* (II-36-73*).

Deviation of the installation parameters of other building structures from the design ones must comply with the requirements of SNiP III-15-76, SNiP III-16-80 and SNiP III-18-75.

3.7. The construction organization project and the work execution project must provide for the advanced construction of drainage pumping stations and water release devices in accordance with the working drawings.

3.8. Before laying in the trench drainage pipes must be inspected and cleared of soil and debris.

3.9. Layer-by-layer filtering of drainage pipelines (except for pipe filters) with gravel and sand must be performed using inventory separation forms.

3.10. The straightness of sections of drainage pipelines between adjacent wells should be checked by inspection “to the light” using a mirror before and after backfilling the trench. The pipe circumference reflected in the mirror must have the correct shape. The permissible horizontal deviation from the circle should be no more than 0.25 of the pipe diameter, but no more than 50 mm in each direction.

Deviation from correct form Vertical circles are not allowed.

4. INSTALLATION OF PIPELINES

4.1. The installation of pipelines must be carried out by specialized installation organizations, and the installation technology must ensure high operational reliability of the pipelines.

4.2. Parts and pipeline elements (expansion joints, mud traps, insulated pipes, as well as pipeline assemblies and other products) must be manufactured centrally (in factories, workshops, workshops) in accordance with standards, technical specifications and design documentation.

4.3. Laying of pipelines in a trench, channel or on above-ground structures should be carried out according to the technology provided for by the work project and excluding the occurrence of residual deformations in the pipelines, violation of the integrity of the anti-corrosion coating and thermal insulation by using appropriate installation devices, correct placement simultaneously operating lifting machines and mechanisms.

The design of fastening mounting devices to pipes must ensure the safety of the coating and insulation of pipelines.

4.4. The laying of pipelines within the panel support must be carried out using pipes of the maximum delivery length. In this case, the welded transverse seams of pipelines should, as a rule, be located symmetrically relative to the panel support.

4.5. Laying of pipes with a diameter of over 100 mm with a longitudinal or spiral seam should be carried out with an offset of these seams by at least 100 mm. When laying pipes with a diameter of less than 100 mm, the displacement of the seams must be at least three times the thickness of the pipe wall.

Longitudinal seams must be within the upper half of the circumference of the pipes being laid.

Steeply curved and stamped pipeline bends are allowed to be welded together without a straight section.

Welding of pipes and bends into welded joints and bent elements is not allowed.

4.6. When installing pipelines, the movable supports and hangers must be shifted relative to the design position by the distance specified in the working drawings, in the direction opposite to the movement of the pipeline in working condition.

In the absence of data in the working drawings, the movable supports and hangers of horizontal pipelines must be shifted taking into account the correction for the outside air temperature during installation by the following values:

sliding supports and elements for fastening hangers to the pipe - by half the thermal elongation of the pipeline at the attachment point;

roller bearing rollers - by a quarter of thermal elongation.

4.7. When installing pipelines, spring hangers must be tightened in accordance with the working drawings.

During runtime hydraulic tests For steam pipelines with a diameter of 400 mm or more, a unloading device should be installed in spring suspensions.

4.8. Pipe fittings must be installed in a closed state. Flange and welded connections of fittings must be made without tension in the pipelines.

The deviation from the perpendicularity of the plane of the flange welded to the pipe relative to the pipe axis should not exceed 1% of the outer diameter of the flange, but be no more than 2 mm at the top of the flange.

4.9. Bellows (wavy) and stuffing box expansion joints should be installed assembled.

When laying heating networks underground, installation of compensators in the design position is allowed only after preliminary tests of the pipelines for strength and tightness, backfill channelless pipelines, channels, chambers and panel supports.

4.10. Axial bellows and stuffing box expansion joints should be installed on pipelines without breaking the axes of the expansion joints and the axes of the pipelines.

Permissible deviations from the design position of the connecting pipes of compensators during their installation and welding should be no more than those specified in the technical specifications for the manufacture and supply of compensators.

4.11. When installing bellows expansion joints, they are not allowed to twist relative to the longitudinal axis and sag under the influence of their own weight and the weight of adjacent pipelines. Slinging of expansion joints should be done only by the pipes.

4.12. The installation length of bellows and stuffing box expansion joints must be taken according to the working drawings, taking into account corrections for the outside air temperature during installation.

Stretching of expansion joints to the installation length should be done using devices provided for in the design of expansion joints, or tensioning mounting devices.

4.13. Stretching of the U-shaped compensator should be carried out after completion of pipeline installation, quality control of welded joints (except for closing joints used for tension) and fastening of fixed support structures.

The compensator should be stretched by the amount indicated in the working drawings, taking into account the correction for the outside air temperature when welding the closing joints.

Stretching of the compensator must be carried out simultaneously on both sides at joints located at a distance of no less than 20 and no more than 40 pipeline diameters from the axis of symmetry of the compensator, using tension devices, unless other requirements are justified by the design.

On the section of the pipeline between the joints used for stretching the compensator, there should be no preliminary displacement of supports and hangers in comparison with the design (detailed design).

4.14. Immediately before assembling and welding pipes, it is necessary to visually inspect each section to ensure that there are no foreign objects or debris in the pipeline.

4.15. Deviation of the pipeline slope from the design is allowed by +/- 0.0005. In this case, the actual slope must be no less than the minimum allowable according to SNiP II-G.10-73* (II-36-73*).

Movable pipeline supports must be adjacent to the supporting surfaces of structures without gaps or distortion.

4.16. When performing installation work, the following types of hidden work are subject to acceptance with drawing up inspection reports in the form given in SNiP 3.01.01-85: preparation of the surface of pipes and welded joints for anti-corrosion coating; performing anti-corrosion coating of pipes and welded joints.

A report on the stretching of compensators should be drawn up in the form given in the mandatory Appendix 1.

4.17. Protection of heating networks from electrochemical corrosion must be carried out in accordance with the Instructions for the protection of heating networks from electrochemical corrosion, approved by the USSR Ministry of Energy and the Ministry of Housing and Utilities of the RSFSR and agreed with the USSR State Construction Committee.

5. ASSEMBLY, WELDING AND QUALITY CONTROL OF WELDED JOINTS

5.1. Welders are allowed to tack and weld pipelines if they have documents authorizing them to carry out welding work in accordance with the Rules for the Certification of Welders approved by the USSR State Mining and Technical Supervision.

5.2. Before being allowed to work on welding pipeline joints, the welder must weld the permitted joint in production conditions in the following cases:

with a break in work for more than 6 months;

when welding pipelines with changes in steel group, welding materials, technology or welding equipment.

On pipes with a diameter of 529 mm or more, it is allowed to weld half the perimeter of the permissible joint; Moreover, if the permissible joint is vertical and non-rotating, the ceiling and vertical sections of the seam must be welded.

The permissible joint must be of the same type as the production joint (the definition of a joint of the same type is given in the Rules for Certification of Welders of the USSR State Mining and Technical Supervision).

The permissible joint is subject to the same types of control that production welded joints are subjected to in accordance with the requirements of this section.

Manufacturing jobs

5.3. The welder is obliged to knock out or fuse the mark at a distance of 30-50 mm from the joint on the side accessible for inspection.

5.4. Before assembly and welding, it is necessary to remove the end caps, clean until pure metal edges and adjacent internal and external surfaces of pipes to a width of at least 10 mm.

5.5. Welding methods, as well as types, structural elements and dimensions of welded joints of steel pipelines must comply with GOST 16037-80.

5.6. Pipeline joints with a diameter of 920 mm or more, welded without a remaining backing ring, must be made with welding of the root of the seam inside the pipe. When welding inside a pipeline, the responsible person must be issued a permit to carry out the work. increased danger. The issuance procedure and form of the permit must comply with the requirements of SNiP III-4-80.

5.7. When assembling and welding pipe joints without a backing ring, the displacement of the edges inside the pipe should not exceed:

for pipelines that are subject to the requirements of the USSR State Mining and Technical Supervision Rules - in accordance with these requirements;

for other pipelines - 20% of the pipe wall thickness, but not more than 3 mm.

In pipe joints assembled and welded on the remaining backing ring, the gap between the ring and inner surface pipes should not exceed 1 mm.

5.8. The assembly of pipe joints for welding should be done using mounting centering devices.

Correction of smooth dents at the ends of pipes for pipelines that are not subject to the requirements of the USSR Gosgortekhnadzor Rules is allowed if their depth does not exceed 3.5% of the pipe diameter. Sections of pipes with deeper dents or tears should be cut out. The ends of pipes with nicks or chamfers with a depth of 5 to 10 mm should be cut off or corrected by surfacing.

5.9. When assembling a joint using tacks, their number should be for pipes with a diameter up to 100 mm - 1 - 2, with a diameter over 100 to 426 mm - 3 - 4. For pipes with a diameter over 426 mm, tacks should be placed every 300-400 mm around the circumference.

The tacks should be evenly spaced around the perimeter of the joint. The length of one tack for pipes with a diameter of up to 100 mm is 10 - 20 mm, with a diameter over 100 to 426 mm - 20 - 40, with a diameter over 426 mm - 30 - 40 mm. The tack height should be for a wall thickness S up to 10 mm - (0.6 - 0.7) S, but not less than 3 mm, for a larger wall thickness - 5 - 8 mm.

The electrodes or welding wire used for tack welding must be of the same grade as that used for welding the main seam.

5.10. Welding of pipelines that are not subject to the requirements of the USSR State Mining and Technical Supervision Rules may be carried out without heating the welded joints:

at outside air temperatures down to minus 20 degrees C - when using pipes made of carbon steel with a carbon content of no more than 0.24% (regardless of the wall thickness of the pipes), as well as pipes made of low-alloy steel with a wall thickness of no more than 10 mm;

at outside air temperatures down to minus 10 degrees C - when using pipes made of carbon steel with a carbon content of over 0.24%, as well as pipes made of low-alloy steel with a wall thickness of over 10 mm.

At lower outside temperatures, welding should be carried out in special booths, in which the air temperature in the area of ​​​​the welded joints should be maintained not lower than the specified one.

It is allowed to carry out welding work in the open air by heating the welded ends of pipes at a length of at least 200 mm from the joint to a temperature of at least 200 degrees C. After welding is completed, a gradual decrease in the temperature of the joint and the adjacent pipe area must be ensured by covering them with asbestos sheets or using another method.

Welding (at negative temperature) pipelines, which are subject to the requirements of the USSR State Mining and Technical Supervision Rules, must be carried out in compliance with the requirements of these Rules.

In rain, wind and snow, welding work can only be carried out if the welder and the welding site are protected.

5.11. Welding of galvanized pipes should be carried out in accordance with SNiP 3.05.01-85.

5.12. Before welding pipelines, each batch of welding materials (electrodes, welding wire, fluxes, shielding gases) and pipes must be subjected to incoming inspection:

for a certificate with verification of the completeness of the data contained in it and their compliance with the requirements of state standards or technical specifications;

to ensure that each box or other package contains a corresponding label or tag with verification of the data on it;

for the absence of damage (damage) to the packaging or the materials themselves. If damage is detected, the question of the possibility of using these welding materials must be resolved by the organization performing the welding;

on the technological properties of electrodes in accordance with GOST 9466-75 or departmental regulatory documents, approved in accordance with SNiP 1.01.02-83.

5.13. When applying the main seam, it is necessary to completely overlap and weld the tacks.

Quality control

5.14. Quality control of welding work and welded joints of pipelines should be carried out by:

checking the serviceability of welding equipment and measuring instruments, quality of materials used;

operational control during the assembly and welding of pipelines;

external inspection of welded joints and measurements of seam sizes;

checking the continuity of joints non-destructive methods control - radiographic (X-ray or gamma rays) or ultrasonic flaw detection in accordance with the requirements of the USSR State Mining and Technical Supervision Rules, GOST 7512-82, GOST 14782-76 and other standards approved in the prescribed manner. For pipelines that are not subject to the USSR State Mining and Technical Supervision Rules, it is allowed to use magnetographic testing instead of radiographic or ultrasonic testing;

mechanical tests and metallographic studies of control welded joints of pipelines, which are subject to the requirements of the USSR State Mining and Technical Supervision Rules, in accordance with these Rules;

tests for strength and tightness.

5.15. At operational control the quality of welded joints of steel pipelines must be checked for compliance with standards structural elements and dimensions of welded joints (blunting and cleaning of edges, the size of the gaps between the edges, the width and reinforcement of the weld), as well as welding technology and mode, the quality of welding materials, tacks and welds.

5.16. All welded joints are subject to external inspection and measurement.

Pipeline joints welded without a backing ring with weld root welding are subject to external inspection and measurement of the dimensions of the seam outside and inside the pipe, in other cases - only from the outside. Before inspection, the weld seam and the adjacent surfaces of the pipes must be cleaned of slag, splashes of molten metal, scale and other contaminants to a width of at least 20 mm (on both sides of the seam).

The results of external inspection and measurement of dimensions of welded joints are considered satisfactory if:

there are no cracks of any size and direction in the seam and the adjacent area, as well as undercuts, sagging, burns, unsealed craters and fistulas;

the dimensions and number of volumetric inclusions and depressions between the rollers do not exceed the values ​​​​given in table. 1;

the dimensions of lack of penetration, concavity and excess penetration at the root of the weld of butt joints made without a remaining backing ring (if it is possible to inspect the joint from inside the pipe) do not exceed the values ​​​​given in table. 2.

Joints that do not meet the listed requirements must be corrected or removed.

Table 1

Maximum allowed
linear size of the defect, mm

Maximum
acceptable
number of defects for any 100 mm of seam length

Volumetric inclusion of a round or elongated shape with a nominal wall thickness of welded pipes in butt joints or smaller weld leg in corner joints, mm:

St. 5.0 to 7.5

Recession (deepening) between the rollers and scaly structure of the weld surface with the nominal wall thickness of the pipes being welded in butt joints or with a smaller weld leg in corner joints, mm:

Not limited

table 2

Pipelines,
for which
Rules of Gosgortekhnadzor of the USSR

Maximum permissible height (depth), % of nominal wall thickness

Maximum permissible total length along the perimeter of the joint

Spread

Concavity and lack of penetration at the root of the seam
Exceeding penetration

10, but not more than 2 mm

20, but not more than 2 mm

20% perimeter

Do not apply

Concavity, excess penetration and lack of penetration at the root of the weld

1/3
perimeter

5.17. Welded joints are subjected to continuity testing using non-destructive testing methods:

pipelines that are subject to the requirements of the USSR State Mining and Technical Supervision Rules, with an outer diameter of up to 465 mm - in the volume provided for by these Rules, with a diameter over 465 to 900 mm in a volume of at least 10% (but not less than four joints), with a diameter over 900 mm - in the volume not less than 15% (but not less than four joints) total number similar joints made by each welder;

pipelines that are not subject to the requirements of the USSR State Mining and Technical Supervision Rules, with an outer diameter of up to 465 mm in a volume of at least 3% (but not less than two joints), with a diameter over 465 mm - in a volume of 6% (but not less than three joints) of the total number of similar joints performed by each welder; in case of checking the continuity of welded joints using magnetic testing, 10% of the total number of joints subjected to control must also be checked using the radiographic method.

5.18. Non-destructive testing methods should be applied to 100% of welded joints of heating network pipelines laid in non-passable channels under roadways, in cases, tunnels or technical corridors together with other engineering communications, as well as at intersections:

railways and tram tracks - at a distance of at least 4 m, electrified railways - at least 11 m from the axis of the outermost track;

railways of the general network - at a distance of at least 3 m from the nearest roadbed structure;

highways - at a distance of at least 2 m from the edge of the roadway, reinforced shoulder strip or the bottom of the embankment;

metro - at a distance of at least 8 m from structures;

power, control and communication cables - at a distance of at least 2 m;

gas pipelines - at a distance of at least 4 m;

main gas and oil pipelines - at a distance of at least 9 m;

buildings and structures - at a distance of at least 5 m from walls and foundations.

5.19. Welds should be rejected if, when tested by non-destructive testing methods, cracks, unwelded craters, burns, fistulas, as well as lack of penetration at the root of the weld made on the backing ring are detected.

5.20. When checking by radiographic method the welded seams of pipelines, which are subject to the requirements of the USSR Gosgortekhnadzor Rules, pores and inclusions are considered acceptable defects, the dimensions of which do not exceed the values ​​​​specified in Table. 3.

Table 3

Nominal
wall thickness

Maximum permissible sizes of pores and inclusions, mm

Total pore length and

individual

clusters

inclusions

width (diameter)

width (diameter)

width (diameter)

for any 100 mm seam, mm

St. 2.0 to 3.0

The height (depth) of lack of penetration, concavity and excess penetration at the root of the weld of a joint made by one-sided welding without a backing ring should not exceed the values ​​​​specified in table. 2.

Acceptable defects in welds according to the results of ultrasonic testing are considered to be defects, measured characteristics, the number of which does not exceed those indicated in the table. 4.

Table 4

Nominal wall thickness

Artificial size

Valid conditional

Number of defects for any 100 mm seam

pipes, mm

corner reflector (“notches”),
mm x mm

length of an individual defect, mm

large and small in total

large

From 4.0 to 8.0

St. 8.0 " 14.5

Notes: 1. A defect is considered large if its nominal length exceeds 5.0 mm for a wall thickness of up to 5.5 mm and 10 mm for a wall thickness of over 5.5 mm. If the conditional length of the defect does not exceed the specified values, it is considered minor.

2. When electric arc welding without a backing ring with one-sided access to the seam, the total conditional length of defects located at the root of the seam is allowed up to 1/3 of the pipe perimeter.

3. The amplitude level of the echo signal from the defect being measured should not exceed the amplitude level of the echo signal from the corresponding artificial corner reflector (“notch”) or equivalent segmental reflector.

5.21. For pipelines that are not subject to the requirements of the USSR Gosgortekhnadzor Rules, acceptable defects in the radiographic inspection method are pores and inclusions, the dimensions of which do not exceed the maximum permissible according to GOST 23055-78 for class 7 welded joints, as well as lack of penetration, concavity and excess penetration at the root of a seam made by one-sided electric arc welding without a backing ring, the height (depth) of which should not exceed the values ​​​​specified in table. 2.

5.22. When non-destructive testing methods are used to identify unacceptable defects in pipeline welds that are subject to the requirements of the USSR Gosgortekhnadzor Rules, repeated quality control of the seams established by these Rules must be carried out, and in pipeline welds that are not subject to the requirements of the Rules - in double the number of joints according to compared to that specified in clause 5.17.

If unacceptable defects are detected during re-inspection, all joints made by this welder must be inspected.

5.23. Sections of the weld with unacceptable defects are subject to correction by local sampling and subsequent welding (without re-welding the entire joint), if the sample size after removing the defective section does not exceed the values ​​​​indicated in the table. 5.

Welded joints, in the seams of which, in order to correct the defective area, it is necessary to make a sample with dimensions larger than those allowed according to the table. 5 must be completely removed.

Table 5

Sampling depth
% of the nominal wall thickness of welded pipes
(calculated height of the seam section)

Length,
% of the nominal outer perimeter of the pipe (nozzle)

St. 25 to 50

No more than 50

Note. When correcting several sections in one connection, their total length may exceed that indicated in the table. 5 no more than 1.5 times at the same depth standards.

5.24. Undercuts should be corrected by surfacing thread beads with a width of no more than 2.0 - 3.0 mm. Cracks must be drilled at the ends, cut out, thoroughly cleaned and welded in several layers.

5.25. All corrected areas of welded joints must be checked by external inspection, radiographic or ultrasonic flaw detection.

5.26. On the as-built drawing of the pipeline, drawn up in accordance with SNiP 3.01.03-84, the distances between welded joints, as well as from wells, chambers and customer inputs to the nearest welded joints, should be indicated.

6. THERMAL INSULATION OF PIPELINES

6.1. Installation of thermal insulation structures and protective coatings must be produced in accordance with the requirements of SNiP III-20-74 and this section.

6.2. Welded and flanged connections should not be insulated to a width of 150 mm on both sides of the connections before testing the pipelines for strength and tightness.

6.3. The possibility of carrying out insulation work on pipelines subject to registration in accordance with the Rules of the USSR Gosgortekhnadzor, before performing strength and tightness tests, must be agreed with the local body of the USSR Gosgortekhnadzor.

6.4. When performing flooded and backfill insulation during channelless laying of pipelines, the work design must include temporary devices to prevent the pipeline from floating up, as well as soil from getting into the insulation.

7. TRANSITIONS OF HEATING NETWORKS THROUGH DRIVEWAYS AND ROADS

7.1. Work at underground (aboveground) intersections of heating networks with railways and tramways, roads, city passages should be carried out in accordance with the requirements of these rules, as well as SNiP III-8-76.

7.2. When piercing, punching, horizontal drilling or other methods of trenchless laying of casings, assembly and tack of casing links (pipes) must be performed using a centralizer. The ends of the welded links (pipes) must be perpendicular to their axes. Fractures of the axes of the links (pipes) of the cases are not allowed.

7.3. Reinforced shotcrete anti-corrosion coating of cases during trenchless installation should be made in accordance with the requirements of SNiP III-15-76.

7.4. Pipelines within the casing should be made from pipes of the maximum supplied length.

7.5. The deviation of the axis of the transition cases from the design position for gravity condensate pipelines should not exceed:

vertically - 0.6% of the length of the casing, provided that the design slope of the condensate pipelines is ensured;

horizontally - 1% of the length of the case.

The deviation of the axis of the transition casings from the design position for the remaining pipelines should not exceed 1% of the casing length.

8. TESTING AND WASHING (BLOWING) OF PIPELINES

8.1. After completion of construction and installation work, pipelines must be subjected to final (acceptance) tests for strength and tightness. In addition, condensate pipelines and pipelines of water heating networks must be washed, steam pipelines must be purged with steam, and pipelines of water heating networks with an open heating supply system and hot water supply network must be washed and disinfected.

Pipelines laid without channels and in non-passable channels are also subject to preliminary tests for strength and tightness during construction and installation work.

8.2. Preliminary tests of pipelines should be carried out before installing gland (bellows) compensators, sectional valves, closing channels and backfilling of channelless pipelines and channels.

Preliminary tests of pipelines for strength and tightness should be performed, as a rule, hydraulically.

At negative outside temperatures and the impossibility of heating water, as well as in the absence of water, it is allowed, in accordance with the work plan, to perform preliminary tests using a pneumatic method.

It is not allowed to carry out pneumatic tests of above-ground pipelines, as well as pipelines laid in the same channel (section) or in the same trench with existing utilities.

8.3. Pipelines of water heating networks should be tested at a pressure equal to 1.25 working, but not less than 1.6 MPa (16 kgf/sq.cm), steam pipelines, condensate pipelines and hot water supply networks - at a pressure equal to 1.25 working, unless other requirements justified by the project (working project).

8.4. Before performing strength and tightness tests, you must:

carry out quality control of welded joints of pipelines and correction of detected defects in accordance with the requirements of Section. 5;

disconnect the tested pipelines with plugs from the existing ones and from the first shut-off valves installed in the building (structure);

install plugs at the ends of the tested pipelines and instead of stuffing box (bellows) compensators, sectional valves during preliminary tests;

provide access along the entire length of the tested pipelines for their external inspection and inspection of welds during the tests;

open the valves and bypass lines completely.

The use of shut-off valves to disconnect the pipelines under test is not permitted.

Simultaneous preliminary tests of several pipelines for strength and tightness may be carried out in cases justified by the work design.

8.5. Pressure measurements when testing pipelines for strength and tightness should be made using two duly certified (one control) spring pressure gauges of class not lower than 1.5 with a body diameter of at least 160 mm and a scale with a nominal pressure of 4/3 of the measured pressure.

8.6. Testing of pipelines for strength and tightness (density), their purging, washing, disinfection must be carried out according to technological schemes(agreed with operating organizations), regulating the technology and safety precautions for carrying out work (including the boundaries of security zones).

8.7. Reports on the results of tests of pipelines for strength and tightness, as well as on their flushing (purging) should be drawn up in the forms given in mandatory appendices 2 and 3.

Hydraulic tests

8.8. Pipeline testing should be carried out in compliance with the following basic requirements:

test pressure must be provided at the top point (mark) of the pipelines;

the water temperature during testing must be no lower than 5 degrees C;

if the outside air temperature is negative, the pipeline must be filled with water at a temperature not exceeding 70 degrees C and it must be possible to fill and empty it within 1 hour;

when gradually filling with water, air must be completely removed from the pipelines;

the test pressure must be maintained for 10 minutes and then reduced to operating pressure;

at operating pressure, the pipeline must be inspected along its entire length.

8.9. The results of hydraulic tests for the strength and tightness of the pipeline are considered satisfactory if during the tests there was no pressure drop, no signs of rupture, leakage or fogging were found in the welds, as well as leaks in the base metal, flange connections, fittings, compensators and other pipeline elements , there are no signs of shifting or deformation of pipelines and fixed supports.

Pneumatic tests

8.10. Pneumatic tests should be carried out for steel pipelines with a working pressure not higher than 1.6 MPa (16 kgf/sq.cm) and a temperature of up to 250 degrees C, mounted from pipes and parts tested for strength and tightness (density) by the manufacturers in accordance with GOST 3845-75 (in this case, the factory test pressure for pipes, fittings, equipment and other products and parts of the pipeline must be 20% higher than the test pressure adopted for the installed pipeline).

The installation of cast iron fittings (except for valves made of ductile cast iron) is not allowed during testing.

8.11. Filling the pipeline with air and increasing the pressure should be done smoothly at a speed of no more than 0.3 MPa (3 kgf/sq.cm) per hour. Visual inspection of the route [entry into the security (dangerous) zone, but without descending into the trench] is allowed when pressure equal to 0.3 test, but not more than 0.3 MPa (3 kgf/sq.cm).

During the inspection of the route, the pressure rise must be stopped.

When the test pressure value is reached, the pipeline must be maintained to equalize the air temperature along the length of the pipeline. After equalizing the air temperature, the test pressure is maintained for 30 minutes and then smoothly decreases to 0.3 MPa (3 kgf/sq.cm), but not higher than the operating pressure of the coolant; At this pressure, pipelines are inspected and defective areas are marked.

Leak locations are determined by the sound of leaking air, bubbles when covering welded joints and other places with soap emulsion and the use of other methods.

Defects are eliminated only by reducing overpressure to zero and turning off the compressor.

8.12. The results of preliminary pneumatic tests are considered satisfactory if during their conduct there is no drop in pressure on the pressure gauge, no defects are found in welds, flange connections, pipes, equipment and other elements and products of the pipeline, and there are no signs of shift or deformation of the pipeline and fixed supports.

8.13. Pipelines of water networks in closed systems heating supplies and condensate pipelines should, as a rule, be subjected to hydropneumatic flushing.

Hydraulic flushing with reuse of flushing water by passing it through temporary mud traps installed along the flow of water at the ends of the supply and return pipelines is allowed.

Washing should usually be done technical water. Washing with household and drinking water is allowed with justification in the work project.

8.14. Water network pipelines open systems heating and hot water supply networks must be flushed hydropneumatically with potable water until the flushing water is completely clarified. After flushing, the pipelines must be disinfected by filling them with water containing active chlorine at a dose of 75-100 mg/l with a contact time of at least 6 hours. Pipelines with a diameter of up to 200 mm and a length of up to 1 km are permitted, in agreement with local sanitary authorities. epidemiological service, do not chlorinate and limit yourself to washing with water that meets the requirements of GOST 2874-82.

After washing, the results of laboratory analysis of wash water samples must comply with the requirements of GOST 2874-82. The sanitary and epidemiological service draws up a conclusion on the results of washing (disinfection).

8.15. The pressure in the pipeline during flushing should not be higher than the working pressure. The air pressure during hydropneumatic flushing should not exceed operating pressure coolant and be no higher than 0.6 MPa (6 kgf/sq.cm).

Water velocities during hydraulic flushing must be no lower than the calculated coolant velocities indicated in the working drawings, and during hydropneumatic flushing - exceed the calculated ones by at least 0.5 m/s.

8.16. Steam lines must be purged with steam and discharged into the atmosphere through specially installed purge pipes with shut-off valves. To warm up the steam line before purging, all start-up drains must be open. The heating rate should ensure that there are no hydraulic shocks in the pipeline.

The steam velocities when blowing each section must be no less than the operating velocities at the design parameters of the coolant.

9. ENVIRONMENTAL PROTECTION

9.1. When constructing new, expanding and reconstructing existing heating networks, environmental protection measures should be taken in accordance with the requirements of SNiP 3.01.01-85 and this section.

9.2. It is not allowed without agreement with the relevant service: to produce excavation at a distance of less than 2 m to tree trunks and less than 1 m to bushes; moving loads at a distance of less than 0.5 m to tree crowns or trunks; storing pipes and other materials at a distance of less than 2 m from tree trunks without installing temporary enclosing (protective) structures around them.

9.3. Hydraulic flushing of pipelines should be done by reusing water. Emptying of pipelines after washing and disinfection should be carried out in places specified in the work project and agreed upon with the relevant services.

9.4. Territory construction site after completion of construction and installation work, it must be cleared of debris.

Appendix 1. ACT ON STRETCHING OF COMPENSATORS

ANNEX 1
Mandatory

________________________ "_____"_________________19_____

Commission consisting of:


(last name, first name, patronymic, position)

_____________________________________________________________,

1. The extension of expansion joints listed in the table in the area from chamber (picket, shaft) No. _______ to chamber (picket, shaft) No. _______ was presented for inspection and acceptance.

Compensator number

Drawing number

Type of compensation

Stretch value, mm

Temperature
outdoor

according to drawing

design

actual

air, degrees C

2. The work was carried out according to design estimates ____________

_______________________________________________________________

COMMISSION DECISION

The work was carried out in accordance with design and estimate documentation, state standards, building codes and rules and meet the requirements for their acceptance.


(signature)


(signature)

Appendix 2. ACT ON TESTING PIPELINES FOR STRENGTH AND TIGHTNESS

APPENDIX 2
Mandatory

_____________________ "_____"____________19____

Commission consisting of:

representative of the construction and installation organization _________________

_____________________________________________________________,
(last name, first name, patronymic, position)

representative of the customer's technical supervision _____________________

_____________________________________________________________,
(last name, first name, patronymic, position)

representative of the operating organization ______________________________

_____________________________________________________________
(last name, first name, patronymic, position)

inspected the work performed by ___________________________

_____________________________________________________________,
(name of construction and installation organization)

and drew up this act as follows:

1. ________________ are presented for inspection and acceptance

_____________________________________________________________
(hydraulic or pneumatic)

pipelines tested for strength and tightness and listed in the table, in the section from chamber (picket, shaft) No. ________ to chamber (picket, shaft) No. _________ route ___________

Length __________ m.
(name of pipeline)

Pipeline

Test pressure
MPa (kgf/sq.cm)

Duration, min

External inspection at pressure, MPa (kgf/sq.cm)

2. The work was carried out according to design and estimate documentation __________________

_____________________________________________________________________
(name of the design organization, drawing numbers and date of their preparation)

COMMISSION DECISION

Representative of the construction and installation organization ________________
(signature)

Representative of the customer's technical supervision _____________________
(signature)


(signature)

Appendix 3. ACT ON WASHING (BLOWING) OF PIPELINES

APPENDIX 3
Mandatory

_______________________________________ "_____"_______________19_____

Commission consisting of:

representative of the construction and installation organization ________________

_____________________________________________________________,
(last name, first name, patronymic, position)

representative of the customer's technical supervision _____________________

_____________________________________________________________,
(last name, first name, patronymic, position)

representative of the operating organization _____________________

_____________________________________________________________
(last name, first name, patronymic, position)

inspected the work performed by ____________________________

_____________________________________________________________,
(name of construction and installation organization)

and drew up this act as follows:

1. Flushing (purging) of pipelines in the section from chamber (picket, shaft) No. __________ to chamber (picket, shaft) No.______ of the route ________________________________________________________________________________ is submitted for inspection and acceptance.

_____________________________________________________________________________________
(name of pipeline)

length ___________ m.

Washing (purging) completed________________________________

_____________________________________________________________.
(name of medium, pressure, flow)

2. The work was carried out according to design estimates _________________

____________________________________________________________________

_____________________________________________________________________.
(name of the design organization, drawing numbers and date of their preparation)

COMMISSION DECISION

The work was carried out in accordance with design and estimate documentation, standards, building codes and regulations and meets the requirements for their acceptance.

Representative of the construction and installation organization ________________
(signature)

Representative of the customer's technical supervision _____________________
(signature)

Representative of the operating organization _____________________
(signature)

The text of the document is verified according to:
official publication
M.: CITP Gosstroy USSR, 1986

Rules for the installation and installation of compensators.

1. Bellows, lens and stuffing box expansion joints should be installed assembled.
2. Axial bellows, lens and stuffing box expansion joints should be installed coaxially with the pipelines.

Permissible deviations from the design position of the connecting pipes of compensators during their installation and welding should be no more than those specified in the technical specifications for the manufacture and supply of compensators.

3. When installing lens, wavy and stuffing box compensators, as well as fittings, the direction of the arrow on their body must coincide with the direction of movement of the substance in the pipeline.

4. When installing bellows and lens compensators, twisting loads relative to the longitudinal axis and sagging under the influence of its own weight and the weight of adjacent pipelines should be eliminated, and the flexible element should be protected from mechanical damage and sparks during welding.

5. The installation length of bellows, lens and stuffing box expansion joints must be taken according to the working drawings, taking into account corrections for the outside air temperature during installation.

6. To compensate for temperature deformations of pipelines during installation, U-shaped, bellows, lens and gland compensators must be installed with tension (compression) by the value specified in the design. If the air temperature at the time of installation differs from that accepted in the project, then the amount of tension (compression) of the compensator should be increased (if tension is specified in the project) or decreased (if compression is specified) by the value (mm):

в=aL(t p +t m)

a is the temperature coefficient of linear expansion of the pipeline metal, °C -1, accepted for carbon and low-alloy steels 0.012 and high-alloy steels - 0.017;
L is the estimated length of the pipeline section, m;
t p - air temperature adopted in the project at the time of installation, °C;
t m - actual air temperature at the time of installation, °C.

7. When installing stuffing box expansion joints, the free movement of moving parts and the safety of the packing must be ensured.
8. Installation of single-section axial bellows, lens, stuffing box and U-shaped expansion joints with devices for stretching is carried out in the following sequence (Figure 1, a):

Expansion joints should be stretched to the installation length using devices provided by the compensator design or tension mounting devices.

Damn.1. Sequence of operations (1-5) when installing compensators:

A - U-shaped, axial bellows single-section, lens and stuffing box with a device for stretching;
b - the same without a device for stretching;
c - U-shaped compensator for group installation.

a) one side of the compensator is connected by welding or on a flange to the pipeline;
b) a section of the pipeline with an attached compensator is installed in guides and sliding supports and secured in a fixed support.

Note.

Depending on the installation conditions (for example, for U-shaped compensators), the pipeline can first be installed in guides and sliding supports and secured in a fixed support, and then connected to this section of the compensator;

c) with the help of spacer devices, the compensator is subjected to tension by the designed value. It is allowed to pre-stretch the compensator before connecting it to the pipeline;

d) a section of the pipeline on the other side, freely lying in the guides and sliding supports, is pulled to the free joint of the compensator and connected to it by welding or on a flange;

e) the attached section of the pipeline is fixed in another fixed support;

f) the pre-stretching device is removed from the compensator.

11. Installation of axial bellows expansion joints without a tension device is carried out in the following sequence (see Fig. 15, b):

a) a section of the pipeline on one side of the compensator is installed in guides and sliding supports and secured in a fixed support;

b) the pipeline section on the other side of the compensator is installed so that the distance between the ends of the pipeline sections is equal to the installation length of the compensator, and is fixed in another fixed support. The installation length of the compensator must be equal to its construction length(compensator unloaded) plus pre-tension (compression)

c) the compensator is connected to one of the pipeline sections;

d) with the help of mounting devices, the compensator is stretched and connected to another section of the pipeline;

e) mounting devices are removed.

12. When U-shaped expansion joints are arranged in a group (see Figure 15, c) of pipelines laid in parallel, expansion of the expansion joints should be done by tensioning the pipeline in a cold state. In this case, stretching of the U-shaped compensator should be carried out after completing the installation of the pipeline, quality control of welded joints (except for the closing one used for tension) and securing the pipeline in fixed supports.

  1. The welded joint at which the compensator should be stretched is indicated in the design. If there is no such indication, then in order to avoid reducing the compensating ability of the compensator and its distortion, you should use a joint located at a distance of at least 20 days from the axis of the compensator
  2. Removable or welded clamps with mounting extended studs and nuts are used as a tensioning device for tension.
  3. When U-shaped expansion joints are arranged in a group, the installation sequence is as follows:

a) sections of the pipeline and the U-shaped compensator are installed on supports. A wooden spacer with a width of equal to the value sprains;

b) the compensator is connected to the corresponding sections of the pipeline by welding on both sides;

c) the pipeline section is fixed in fixed supports;

d) the spacer is removed, the compensator is pre-tensioned, and the joint is connected by welding;

e) mounting fixtures are removed.

  1. For heating pipelines, in accordance with the requirements of SNiP 3.05.03-85, tension expansion joints should be stretched simultaneously on both sides at joints located at a distance of at least 20 days and no more than 40 days from the axis of symmetry of the compensator
  2. A report on the tension (compression) of the compensator must be drawn up in the form of Appendix 6 of SNiP 3.01.01-85.
  3. U-shaped expansion joints should be installed in compliance with the general slope of the pipeline specified in the project.
  4. Lens, wavy and stuffing box expansion joints are recommended to be installed in pipeline assemblies and blocks during their assembly, using additional rigidity to protect the expansion joints from deformation and damage during transportation, lifting and installation. Upon completion of installation, the temporarily installed rigidities are removed.
  5. When installing vertical sections of pipelines, it is necessary to exclude the possibility of compression of expansion joints under the influence of weight vertical section pipeline. To do this, three brackets should be welded parallel to the expansion joints on the pipelines, which are cut off upon completion of installation.
  6. To determine the correct position of the fittings installed on the pipeline, it is necessary to follow the instructions of catalogs, technical specifications and working drawings. The position of the steering wheel axes is determined by the project.
  7. Pipe fittings must be installed in a closed state. Flange and welded connections of fittings must be made without tension in the pipeline. When welding welded fittings, its shutter should be opened all the way to prevent it from jamming when the body heats up.
Share